Rehabilitation of the Idlib–Ariha road, widened to 25.5 metres by the General Establishment for Road Communications, reached about 50% completion in October 2026.

The Damascus Awqaf Directorate began fit-out works in November 2026 on the Yalbugha Commercial Complex near Marjeh Square in Damascus, now under implementation.

An urban development of 3,716 apartments on 550,000 m2 in Hama near Al-Arbaeen district, with shops, schools, health services and community facilities.

An integrated residential project in Hama near Al-Ittihad roundabout with 1,000 units on 115,000 m2, with education, health, sports and retail facilities.

A mixed-use project at the northern entrance of Hama combining a three-storey mall, a hotel in the concept and three residential towers with about 180 units.

A concept to reconnect the centre of Hama with the Orontes, starting from Al-Mamouriya Square, along about 4.5 km of riverfront in old Hama.

A proposed 149,295 m2 entertainment destination in Hama combining gardens, amusement rides, sports fields, restaurants, an events hall and a zoo.

A concept for a 32,000 m2 public park in Hama beside Al-Ittihad Al-Ummali Street, combining green space, family entertainment and commercial services.

180 View – Living and Investment Destination in Hama, Syria

Engineers Tower – Commercial, Business and Hospitality Project in Hama

Ataa is rehabilitating 235 homes, 25 shops, two mosques and two schools in the Southern Neighborhood of Maarat al-Numan, Idlib, with Qatar Charity funding.

Rebuilding of the strategic Al-Siyasiyeh Bridge over the Euphrates in Deir ez-Zor, executed by the Syrian Establishment for Building and Construction under a 12-month contract. Works began on 29 May 2026, and the executing body expects completion by 29 March 2027.

A hotel, residential and commercial complex near Umayyad Square in central Damascus. Its joint company's development license was announced in September 2026.

An early gas production and processing unit at the Tabiyeh field in Deir ez-Zor, rehabilitated and restarted by Syrian Petroleum Company, producing from two of five wells.

Bab al-Hawa Industrial City in Idlib has begun an expansion that clears a 55,000 square metre rocky mass to add new plots for food industries and strengthen the investment environment.

Rehabilitation of Al-Marjeh Square (Martyrs' Square) in central Damascus under a new design. Works began in late August 2026, according to the Supervision Directorate in Damascus, and include a small lake, fountain rehabilitation, a green lawn and pedestrian paths.

Rehabilitation of the Al-Rastan Strategic Bridge on the M5 highway in Homs Governorate, implemented by the Syrian Civil Defense with UNDP and funded by the Syria Humanitarian Fund. Reopened to traffic on 4 June 2026.

Rehabilitation of the Al-Tuwaina pumping station in Al-Ghab, rural Hama, with FAO, as part of restarting the Afamia water complex serving about 3,000 hectares of farmland.

Rehabilitation and outfitting of a hotel building at the Mazzeh Highway and Southern Ring Road intersection in Damascus, to operate as a luxury hotel.

Renovation and rehabilitation of the emergency department at Hama National Hospital, a US$1 million project under the "Fida'an li-Hama" campaign to strengthen its emergency care capacity.

The Ministry of Health and UNDP signed an agreement in February 2026, funded by Germany through KfW, to rehabilitate and equip five public hospitals for EUR 30 million.

Investment project to develop Aleppo's Western Ring across about 850,000 square metres, with an estimated founding cost of about USD 70 million, in two phases and an expected 3,000+ jobs.

Syria's Ministry of Foreign Affairs and the Aga Khan Development Network signed a memorandum of understanding in Damascus, formalising a commitment of at least €100 million in investment for 2026-2027

SANA reported four substations opened in Al-Sha'ar, Aleppo, on 29 April 2026 with UNDP; the energy minister said power is returning to about 15,000 people.

A 26.5 km metro project with 17 stations to build the first metro line in Damascus (Green Line), serving 840,000 passengers daily.

A 66 kV line linking the Sinjar and Basida substations in rural Idlib, with full rehabilitation of Basida substation and preparations to extend the line toward Al-Bara.

Al-Naser Boulevard: a mixed-use urban development in central Homs with homes, shops, a park and a new wholesale market, under construction since late 2025.

DP World signed a 30-year, $800 million concession in July 2025 to develop and operate Tartus Port, took over its operations in November 2025 and took delivery of three mobile harbour cranes in 2026.

A new courthouse under construction in Safita, Tartus, with two blocks totalling 1,700 m² of floor area, built by SEBCO's Tartus branch; concrete foundation works for Block B began in August 2026.

Douma National Hospital in Rural Damascus was rehabilitated by WHO with funding from Japan and reopened in August 2026 with 40 beds, serving about 550,000 people.

A Syrian–Czech agreement to rehabilitate the Ghazlaniyah water station in Rural Damascus with solar power and a treatment unit, serving 40,000+ beneficiaries.

Rehabilitation of the Al-Sarman silo in southeastern rural Idlib and installation of storage cells, implemented by WFP with the General Establishment for Grains to boost storage capacity.

A specialised oncology hospital in Deir ez-Zor city with about 230 beds and 6 operating rooms, planned as a referral centre for Deir ez-Zor, Raqqa and Hasakah.

Rehabilitation of Zabadani Hospital in Rif Dimashq, including a dialysis department expansion, electrical and lift upgrades, an oxygen system and improved heating and ventilation.

The General Company for Drinking Water and Sanitation in Deir ez-Zor, with MSF, is rehabilitating the Al-Hari water station in eastern rural Al-Bukamal, about 90% complete, to serve around 11,000 people.

Construction of 3,055 metres of roads plus sewage and drinking-water networks in Food Zone (D) of Hassia Industrial City, serving 55 industrial plots.

Zero Pothole, announced by Aleppo Governorate on 19 April 2026 and started on 20 April, covers road repairs in Aleppo city, ten districts and main routes.

A six-tower mixed-use complex in Baramkeh, central Damascus, developed by Souria Holding Company with Damascus Governorate. The governor laid the foundation stone on 11 June 2026, CCC was named design-build contractor in July, and about 15,000 jobs are expected.

Park View is a gated residential community in Yaafour, Rural Damascus, by Unlimited Real Estate & Investment: 420 units in seven residential clusters on about 50,000 m², announced in August 2026 with about 30% of construction done and a reported USD 200 million investment.
.avif)
A residential community developed by Invest Group Overseas (IGO) in Yaafour, west of Damascus, on 144,000 square metres according to SANA. Launched on 17 June 2026; the project website lists 1,280 units in 13 buildings, with handover targeted for Q2 2029.

Al-Fayha Sports Hall in Damascus was rehabilitated at a reported cost of about $3 million and reopened by the Ministry of Sports and Youth on 20 April 2026.

Rehabilitation of the Homs–Hama irrigation network by the Homs Water Resources Directorate with FAO, serving about 13,000 hectares and 200,000 people.

Four-star hotel in Yaafour, Rif Dimashq, with 33 suites, rehabilitated after ceasing operations in 2011, per its investor, and inaugurated on 31 July 2026.

Second phase of restoring 14 historic markets and Khan al-Qaysariyya in old Homs, within a project costing about 11 billion Syrian pounds, carried out through the Syrian Development Organization with donations from merchants and industrialists.

The Ministry of Higher Education announced Tartus University Hospital in July 2026 to serve Tartous University's Faculty of Medicine and offer health services.

Nasaem Aleppo: development in the Urum area west of Aleppo with 125 plots of 500–900 m² on 89,000 m², per a July 2025 post by Imtilak Real Estate.

The Al-Rashid Bridge over the Euphrates in Raqqa was reopened on 6 July 2026 after rehabilitation of an 80-metre damaged section.

Gated villa compound on the Damascus Airport Road with six villa models of 640 to 1,680 m². Imtilak Real Estate gives Q3 2027 as the delivery date.

The General Company for Drinking Water and Sanitation in Hama rehabilitated Qulaydin Station in the Ghab Plain with funding and support from Islamic Relief; it entered trial service in June 2026 with a 255-panel solar system and a 500-cubic-metre reservoir.

Five-hectare integrated sports city offered to investors in Aleppo's Hanano district: covered football pitch, pool, halls, shops and a green space with a lake.

Foundation stone laid in June 2026 for a commercial complex and an automated bakery in the Al-Insha'at district of Homs, on about 5,000 square metres of Syrian Bakeries Establishment land, under what SANA describes as a public-private BOT partnership, with an announced implementation period of 18 months.

The Emergency Response Foundation has begun rehabilitating Uqayribat Health Centre in eastern Hama under the Fidaa li-Hama campaign. According to Rasha Maghmuma of the Hama Health Directorate, the centre is to serve about 80 surrounding villages that lack other health centres, home to some 60,000 people.

Mixed-use development on about 300,000 sq m in Yaafour, Rural Damascus, with retail, offices, homes and a hotel. A contract annex was signed in April 2026.

Idlib Governorate, with the Ministry of Tourism, signed a contract with Bakir Holding Company (Bekir Group Holding) in May 2026 to rehabilitate and operate the Carlton Hotel in Idlib. Four-star: about 60 rooms per the governor, about 76 units per the ministry; opening in about 18 months, per the minister.

Latakia City Council’s design competition for the Southern Corniche walkways produced a winner from about 12 entries, and in April 2026 Latakia Governorate published its details: five integrated zones along the seafront.

W3 is a regulated urban expansion zone in western Aleppo, west of the Jamiyat al-Zahraa neighborhood, covering 240 hectares with about 930 residential plots and room for about 14,000 apartments.

The Palace of Justice in Damascus is undergoing rehabilitation by the General Establishment for Construction and Building to modernize its infrastructure.

A comprehensive rehabilitation of the second and third water pumping stations in Balloran, rural Latakia, carried out by the Latakia Water Establishment with Action For Humanity to raise operating efficiency and keep both stations running.

The UAE company QZ is rehabilitating and operating the grinding mills of the Tartus cement plant under a 15-year contract signed in March 2026 with the state company Omran. Trial production began in April 2026.

Restoration of damaged homes in Al-Umqiyya village in Hama's Al-Ghab Plain, funded by Qatar Charity and carried out by the Emergency Response Foundation in coordination with Hama Governorate; about 281 homes restored by April 2026.

Aleppo's Water Resources Directorate and IYD Relief began rehabilitating the PS8 pump station in Rasem Al-Aboud; Syria's Energy Ministry cited 196 solar panels.

A Model Industrial City in the eastern Aleppo countryside aims to centralize and develop furniture manufacturing within an integrated complex.

Riyadh Cables Group is to invest about SAR 60 million to rehabilitate, operate and develop the Syrian Modern Cables plant in Adra, Rural Damascus, under an 18-year agreement with the Syrian Sovereign Fund.

A planned open-air commercial and recreational boulevard in the Khan al-Asal area west of Aleppo, spanning about 40 hectares.

A hotel and commercial complex in the Mezzeh (Youth City) area of Damascus, developed under the Ministry of Tourism and Damascus Governorate.

Jasmine City is an integrated residential and service development in the Wadi al-Jawz area of Hama, covering about 300,000 square metres.

A proposed mixed-use investment complex (124 dunams) at the Old Fairground overlooking Umayyad Square, with residential towers, a mall, and hotels.

A drinking-water project for villages in rural Salamiyah, Hama, building new transmission lines, implemented by the General Company for Drinking Water and Sanitation in Hama with the Aga Khan Foundation.

Fajr al-Furat is an 18-month project in Deir ez-Zor city to remove building and road rubble and recycle it into construction materials; work began in Al-Rashidiya on 10 September 2026.

The General Establishment for Road Communications has begun widening and rehabilitating the Aleppo – Bab al-Hawa road in the Atareb area, over 8 km, from 10 to 26 metres, to improve traffic and freight flow.

Aleppo Governorate discussed rehabilitating the Al-Babiri water station, east of Aleppo and in service since 1988, with the World Food Programme and UN agencies; WFP announced $600,000 for the project.

Al-Batma water station in eastern rural Homs was rehabilitated with two wells and a solar power system to improve water supply for about 40,000 people in three villages.

Rehabilitating the main water line and household connections in eastern Aleppo to improve drinking-water supply for about 600,000 people, with Alwaleed Philanthropies and UN-Habitat.

announced in Saboura (Rural Damascus) is the "Damascus Towers" project, designed as a large-scale, fully integrated suburban development.

Commercial complex in the Barzeh district of Damascus, developed by the Syrian Engineers Syndicate as a real estate investment for its retirement fund.