Fajr al-Furat is a project to remove rubble from buildings and roads in Deir ez-Zor city and recycle it into raw materials for reconstruction works. Work began on 10 September 2026 in the Al-Rashidiya neighborhood, and the project is planned to last 18 months.
The pilot phase produced six materials with grain sizes from 0 to 2 millimetres up to larger sizes, and they were tested at the Syrian Arab Organization for Standardization and Metrology. The materials are used to make curbstones, interlocking pavers, concrete blocks, asphalt mixes for road paving and non-structural concrete, and are to be offered on the market after official approval by the relevant authorities.
The project is supervised by Deir ez-Zor Governorate and carried out in cooperation between the Deir ez-Zor city council and the Zoom Investment Holding Group.
Works are under way, and rubble removal has started in the Al-Rashidiya neighborhood.