

Core rehabilitation phases at Deir ez-Zor Civil Airport were reported complete in July 2026, with a return to service scheduled for early August 2026. The sections below record the state of the works as reported in April 2026 by the General Authority for Civil Aviation and Air Transport. The percentages cited there apply to individual components rather than to the project as a whole. The dated update at the end of this entry carries the current status.
Deir ez-Zor Civil Airport had been out of civilian service for more than a decade, and the facility was repurposed for military use during the war. The first trial flight returned to the airport on 2 February 2025, when a civilian aircraft arrived from Damascus carrying airport staff and logistical equipment to assess the site's readiness. That flight confirmed the runway required maintenance and that navigation and communications equipment was absent, which framed the scope of the rehabilitation programme that followed.
The Authority's Government Communications Director, Alaa Salal, confirmed that a substantial portion of runway rehabilitation and core facility works had been completed, alongside preliminary technical works on navigation systems. The passenger terminal and administrative offices stood at approximately 90 percent completion, with remaining tasks limited to final finishing works including painting and floor tiling, while air conditioning units were scheduled for installation.
Salal further noted that perimeter wall works and runway maintenance had been fully completed, while maintenance of one of the entrances leading to the aircraft parking apron remained ongoing. Stone cladding works on the administrative buildings and passenger terminal had reached approximately 95 percent, with final finishing continuing across most sections.
Navigation lighting systems were technically ready, pending only the arrival of the lighting equipment for installation and commissioning. Works on the VIP reception hall were also progressing, while landscaping had reached approximately 70 percent completion and entrance gate works stood at the same level.
The Authority's work in that phase focused on three primary tracks:
The Deputy Head of the Authority, Amjad Nakhal, conducted a field visit to the airport to review the progress of infrastructure and operational facility rehabilitation, as part of a comprehensive plan to raise readiness levels ahead of the official reopening. On 2 June 2026, the Head of the General Authority for Civil Aviation, Omar Al-Hassari, held an expanded meeting to discuss the requirements of the final phase and the mechanisms for completing the works in line with the approved timelines, in preparation for returning the airport to service.
Deir ez-Zor Civil Airport is a strategic asset for eastern Syria, and its return to service is expected to alleviate the governorate's isolation, facilitate passenger movement, and support economic activity across the region. The project forms part of a broader national vision aimed at restoring vital facilities in Syrian governorates and expanding domestic air connectivity.
They applied to individual components rather than to the project as a whole: approximately 90 percent for the passenger terminal and administrative offices, approximately 95 percent for stone cladding, and approximately 70 percent for landscaping and entrance gate works. At the end of April 2026 the Authority's chairman put overall completion at 80 to 85 percent.
The General Authority for Civil Aviation and Air Transport is overseeing the project. Its Head is Omar Al-Hassari, its Deputy Head is Amjad Nakhal, and its Government Communications Director is Alaa Salal.
The airport had been out of civilian service for more than a decade and was repurposed for military use during the war. The first trial flight returned on 2 February 2025.
Perimeter wall works and runway maintenance were completed in full. Later works covered final finishes, the installation of air conditioning units, and the installation and commissioning of navigation lighting equipment.
Airport director Firas al-Azzawi announced in July 2026 that the basic and necessary rehabilitation phases had been completed and that the airport was due to return to service in early August 2026.
The airport is a strategic asset for eastern Syria. Its return to service is expected to reduce the governorate's isolation, facilitate passenger movement, and support economic activity, as part of a broader national plan to restore vital facilities and expand domestic air connectivity.
Technical and engineering teams have made significant progress on the ground, bringing the airport closer to operational readiness according to the following milestones:
The project goes beyond mere passenger transport; it carries significant economic and social dimensions:
The project is advancing rapidly as part of a broader government plan to rehabilitate and reactivate vital airports and infrastructure in Syria. Current efforts are focused on ensuring that all facilities strictly comply with civil aviation safety standards before the official announcement of the first flights.

Airport director Firas al-Azzawi announced that the basic and necessary rehabilitation phases had been completed, and that the airport was due to return to service in early August 2026 (SANA, 15 July 2026).
The completion percentages published earlier, in April 2026, applied to specific components rather than to the project as a whole: about 90 percent for the passenger terminal and the administrative offices, about 95 percent for the stone cladding, and about 70 percent for the landscaping and the main entrance gate. At the end of April 2026 the chairman of the General Authority for Civil Aviation and Air Transport, Omar al-Hosari, put overall completion at 80 to 85 percent.
Scheduled commercial service on the Kuwait City route was announced for August 2026. Dates and schedules are reported as published by the cited sources and remain subject to official confirmation.
SANA, Deir ez-Zor airport nears operational readiness
SANA, Deir ez-Zor airport rehabilitation enters final stages
SANA, Civil Aviation Authority continues rehabilitation of Deir ez-Zor airport
Enab Baladi, First trial flight to Deir ez-Zor airport
Arabi21, First civilian flight arrives at Deir ez-Zor airport
