Structural Works Reach 62% Completion at Western Safita School in Tartus

12.08.2026
Structural Works Reach 62% Completion at Western Safita School in Tartus
*Illustrative image

Progress at the Site

The Syrian Establishment for Building and Construction has completed the structural works of the Western Safita school project in Tartus governorate, bringing actual completion to 62%, according to Tartus Governorate. The crews also finished the stone cladding and the interior and exterior plastering of the building.

Finishing and Site Works

  • Tiling, ceramics and carpentry works carried out.
  • Courtyard slabs poured.
  • Enclosure wall built.
  • Roads leading to the school rehabilitated.

Schedule

The governorate states that the works are proceeding within the set timeline. The announcement does not give the contract value, the funding source or an expected handover date.

Share this post
Published on
12.08.2026
Keywords
Safita, Tartus, school construction, Syrian Establishment for Building and Construction, Tartus Governorate

Read More !

Blogs
How to Apply for a Tender in Syria: Procedure, Documents and Issuing Bodies
How to Apply for a Tender in Syria: Procedure, Documents and Issuing Bodies
Read More
Read More
News
Idlib Brings 30 Rehabilitated Health Centres Into Service
Idlib Brings 30 Rehabilitated Health Centres Into Service
Read More
Read More
Square geometric Arabic calligraphy design with interlocking shapes in gray and white.
Updates