overview
The Electricity Transmission Administration (part of the General Electricity Company) in Damascus has announced external and internal request for bids No. 5/2026 for the supply of five 400 kV circuit breakers, under the terms set out in the bidding dossier published on the administration's website.
The required supply covers the following items:
The notice states that the request for bids cannot be divided into lots.
The administration set a delivery period of 6 months and allows partial delivery. The delay penalty is one per thousand of the total contract value for each day of delay beyond the contractual period, capped at 20% of the total contract value.
Bidders remain bound by their offers for 90 days from the final date for submission. Offers are accepted until the end of official working hours on Tuesday, 5 January 2027. The notice does not state an estimated value for the supply.
How to Apply