overview
Hama Health Directorate has announced a full-speed tender for three rehabilitation projects at Suqaylabiyah National Hospital. The works cover the general surgery, outpatient clinics and gynecology departments.
For each project the directorate set the required contractor classification, the execution period and an estimated cost, as follows:
The three estimates add up to SYP 32,277,670.
All projects require a contractor classified in buildings, grade 5 or 6, with an execution period of 120 days per project. The contractor must engage a resident engineer on the project.
A bidder remains bound to its offer for sixty days. The nominated contractor remains bound for ninety days from the date the contract is awarded to it.
Offers may be split, and a separate offer is submitted for each project.