The Contracting Office of the Military Construction Directorate is seeking qualified contractors to carry out electrical works under electrical project no. 69. The request for price offers is issued on an expedited basis and follows the technical conditions of the electricity establishment in Rif Dimashq Governorate.

Scope of Work

The contract covers follow-up of electrical works in Rif Dimashq Governorate (Dimas area) within 30 days. The contractor must:

  • Comply fully with the recommendations of the engineering supervision body.
  • Comply with the technical specifications of the electricity establishment.

Eligibility and Technical Evaluation

Applicants submit a technical file in a sealed envelope, scored out of 100. The minimum score to proceed to the opening of financial offers is 60. The following mandatory items are required, and an offer without them is not accepted:

  • Commercial or industrial register (10 points).
  • Membership of the contractors' syndicate (10 points).
  • Contracts or files of similar works (30 points), stating project name, financial size, client and year.
  • Approved technical staff (20 points), with ID copies, engineering certificates and CVs.

The non-mandatory items are:

  • Previous work with the Military Construction Directorate (10 points), added as a bonus after a good evaluation.
  • Company structure (10 points).
  • Initial execution plan with a suitable timetable (10 points).

Financial Offer and Award

Applicants submit a sealed financial offer for each site, scored out of 100, including:

  • Detailed unit prices in US dollars (90 marks, mandatory).
  • Price analysis (5 marks, non-mandatory).
  • Execution period (5 marks, non-mandatory), awarded for periods under one month.

The offer is accompanied by an undertaking to honour it for 30 days from the submission date, a preliminary bond of USD 1,000 deducted at the finance office of the supervision branch, and a statement of financial solvency, meaning the contractor's ability to finance works if payments are delayed.

Award goes to the lowest-priced offer with the highest results, and the Directorate may negotiate with contractors to reach the price set by the branch.

Execution Terms and Payments

  • Execution period is a maximum of one month from approval and the start-work order, or the period proposed by the contractor if shorter.
  • The delay penalty is 0.015 of the project value for each day of delay, and the project may be withdrawn if the delay exceeds 30 days.
  • Payment is deferred, based on periodic statements certified by the engineering supervision body and the financial procedures approved by the Directorate. The Directorate may withhold 15% of each statement until final handover.
  • Preliminary bonds are returned to unsuccessful bidders and forfeited in full if the winning bidder does not honour its offer.
  • The approved contractor pays a final bond of 5% of the project's initial value.

Bid Opening and General Provisions

A bid-opening committee is formed by decision of the execution branch, and the session is held in closed format. Any offer that fails the technical conditions or the minimum technical score is excluded. An official record of the session is drawn up within one week of the end of the submission period.

The Directorate may award the whole work or part of it, and may re-advertise if a suitable price is not reached. The notice and the resulting contracting procedures are governed by the laws in force at the Ministry of Defense and the financial and administrative regulations of the Military Construction Directorate.

How to Apply