Aleppo Industrial City has announced a third-round sealed-envelope tender for the project to complete the protection wall of the industrial city, under the terms set out in the notice.
The project covers completion of the wall on two sections of the industrial city's road network:
Bidders must keep their offers valid for 120 days. The nominated contractor is bound to its offer for 120 days, starting the day after it is notified of the award. The contractor bears all advertising fees, however many times the notice is published.
The notice requires the contractor to be in the Excellent class, building specialty. The supporting documents required are those set out in the Contracts Law No. 51 of 2004.
The session takes place at the tenders committee's venue, in the office of the head of the Financial Affairs Department at Aleppo Industrial City.
How to Apply