Technical crews at the General Company for Electricity of Quneitra have completed a package of service and rehabilitation projects under the company's investment plan, aiming to improve network reliability and power supply in the governorate's villages and towns, especially areas seeing growing numbers of returning residents.
Company director general Eng. Bashar al-Hamdan told SANA that the works covered 11 transformer stations in several villages, including Ain al-Qadi and Ain al-Zaytoun. Each station was raised from 100 kVA to 200 kVA, which he said improves supply for more than 50 subscribers per station.
Al-Hamdan said the plan focuses on building new transformer stations and replacing, renewing and expanding existing ones. Funds have been allocated for 12 new stations, of which 5 are complete and in service, 3 are under construction, 2 more have been announced, and procedures for taking over the routes of 2 additional stations are being completed.
An underground cable in Jubba, 1.2 km long, was replaced with an overhead line. It feeds the northern part of the village and the main water pump serving the area. Other works included:
He added that an emergency plan operates around the clock to repair any damage to the network.
Several residents expressed satisfaction with the maintenance work, in their words. Kinan al-Khabi of Mesharah said he noticed stronger and steadier current and hoped for fewer rationing hours. Alaa al-Ahmad of Jubba said the new towers and poles improve supply quality and reliability. Shaher al-Tahhan of Madinat al-Salam pointed to efforts to replace damaged conductors and bring power to villages with weak or no supply.
On 10 November, the company began rehabilitating the low-voltage network in Umm Batina, Mamtina, and sections of Nabaa al-Sakhr and Rasm al-Khawalid.